Riverland Battery Power Plant

Riverland Solar Storage is two kilometres to the east of the North-West Bend substation. The site fronts the highway east of Morgan and was previously used for cattle grazing. It will connect to the two existing ElectraNet transmission lines that run through the site.
Solar capacity253MWac
Storage peak / capacity80MW / 320MWh
Site600 hectares
Project AnnouncementMarch 2017 (view the media release)
First community consultation forumMay 2017 (view the media release)
Development application submittedJuly 2017
Connection application submittedJuly 2017
Development application approvedNovember 2017 (view the media release)
Offer to connect issuedPending